Portfolio Details

Plant Room Roof Refurbishment – Leicestershire

Liquid roofing services from Proctor Roofing

A worn felt roof system had been leaking for some time and the bond between the roofing system and the metal deck substrate had broken down, causing the roof to become very bouncy and unstable. Stripping the roof was not an option due to the time of year and the equipment it protected. Maintenance to plant on the roof was also becoming more regular and permanent edge protection was needed. To save money on temporary edge protection, Prockor UK installed the counter balance handrail first to allow roofing works to be carried out safely. A layer of exterior grade plywood was installed over the roof area and fixed through into the metal deck for stability. The roof was then waterproofed with a 25 year cold liquid applied system.

 

 


 

See some of our other work:

You may also like

Help-Desk